OSU-Cascades construction update

At the new campus site, construction crews are continuing work installing the final underground utilities throughout the site that will provide power, natural gas and communications. Once underground utilities are complete, the focus will shift to completing the parking lot – hopefully before winter arrives!

The academic building continues to increase in height, with the second level of the shear walls now poured. Work begins on the third floor walls next week. Work is also progressing on the final building foundations.

Interested community members can also follow the construction progress on our webcam.